[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139677":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139677,798,2,"多选题","根据《建设工程施工合同（示范文本）》,关于变更权的说法，正确的有（）。2018真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人和监理人均可以提出变更",true,{"key":16,"text":17,"correct":18},"B","承包人可以根据施工的需要对工程非重要的部分做出适当变更",false,{"key":20,"text":21,"correct":18},"C","监理人发出变更指示一般无需征得发包人的同意",{"key":23,"text":24,"correct":14},"D","变更指示均通过监理人发出",{"key":26,"text":27,"correct":18},"E","设计变更超过原批准的建设规模时,承包人应先办理规划变更审批手续","AD","本题考查的是工程变更价款的确定。发包人和监理人均可以提出变更。变更指示均通过监理人发出，监理人发出变更指示前应征得发包人同意。选项E应由发包人办理。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]