[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139673":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139673,798,1,"单选题","根据《建设工程施工合同（示范文本）》，下列可能引起合同解除的事件中，属于发包人违约的情形是（）。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","因发包人所在国发生动乱导致合同无法履行连续超过100天",false,{"key":16,"text":17,"correct":14},"B","因罕见暴雨导致合同无法履行连续超过了20天",{"key":19,"text":20,"correct":21},"C","因发包人原因未能在计划开工日期前7天内下达开工通知",true,{"key":23,"text":24,"correct":14},"D","承包人未按进度计划及时完成合同约定工作","本题考查的是合同解除的价款结算与支付。选项C，属于发包人违约解除合同的内容之一。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]