[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139669,798,1,"单选题","某工程合同价6000万元，合同约定:工期6个月，预付款120万元，每月进度款按实际完成工程价款的80%支付；每月再单独支付安全文明施工费50万元；质量保证金按进度款的3%逐月扣留；预付款在最后两个月等额扣回。2018真题承包人每月实际完成工程价款金额如下表，则第2个月发包人实际应支付的工程款金额为（）万元。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","850.0",false,{"key":16,"text":17,"correct":18},"B","826.0",true,{"key":20,"text":21,"correct":14},"C","824.5",{"key":23,"text":24,"correct":14},"D","776.0","本题考查工程进度款支付。预付款最迟应在开工日期前七天内支付，所以第二个月不考虑。则发包人应实际支付金额为（1000×80%）-（1000×80%×3%）+50=826（万元）",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]