[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139665":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139665,798,1,"单选题","某独立土方工程，招标工程量清单中的工程数量为1000m3，承包人投标报价中的综合单价为30元\u002Fm3。合同约定，当实际工程量超过清单工程量15%时调整单价，调整系数为0.9。工程结束时承包人实际完成并经监理工程师确认的工程量为1400m3，则该土方工程的工程量价款为（ ）元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","42300",false,{"key":16,"text":17,"correct":18},"B","41250",true,{"key":20,"text":21,"correct":14},"C","40800",{"key":23,"text":24,"correct":14},"D","37800","本题考查的是工程价款调整。1000×（1+15%）×30+[1400-1000×（1+15%）]×30×0.9=41250元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]