[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139656":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139656,798,1,"单选题","（2019年真题）投标人编制分部分项工程综合单价的主要工作有:①计算清单项目的管理费和利润；②测算人、料、机消耗量；③确定组合定额子目并计算各子目工程量；④确定人、料、机单价，正确的顺序是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","③①②④",false,{"key":16,"text":17,"correct":14},"B","②①③④",{"key":19,"text":20,"correct":14},"C","③②①④",{"key":22,"text":23,"correct":24},"D","③②④①",true,"P234-241 综合单价的计算可以概括为以下步骤: (1)确定组合定额子目； (2)计算定额子目工程量； (3)测算人、料、机消耗量； (4)确定人、料、机单价； (5)计算清单项目的人、料、机总费用； (6)计算清单项目的管理费和利润； (7)计算清单项目的综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]