[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139655,798,1,"单选题","（2019年真题）工程量清单计价模式下，宜采用参数法计价的措施项目费是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","夜间施工增加费",true,{"key":16,"text":17,"correct":18},"B","混凝土模板费",false,{"key":20,"text":21,"correct":18},"C","施工围挡费",{"key":23,"text":24,"correct":18},"D","垂直运输费","P234-241 参数法计价是指按一定的基数乘系数的方法或自定义公式进行计算。这种方法简单明了，但最大的难点是公式的科学性、准确性难以把握。这种方法主要适用于施工过程中必须发生，但在投标时很难具体分项预测，又无法单独列出项目内容的措施项目。如夜间施工费、二次搬运费、冬雨期施工的计价均可以采用该方法。 混凝土模板、脚手架、垂直运输可以采用综合单价法。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]