[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139649":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139649,798,2,"多选题","工程量清单招标时，投标人编制投标报价前应认真复核工程量清单中的分部分项工程量，因为该工程量会影响（ ）（2016）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工方法选择",true,{"key":16,"text":17,"correct":14},"B","投标总价的计算",{"key":19,"text":20,"correct":14},"C","劳动力和机具的选择",{"key":22,"text":23,"correct":24},"D","结算工程量的确定",false,{"key":26,"text":27,"correct":14},"E","投标综合单价报价","ABCE","在编制投标报价之前，需要先对清单工程量进行复核。因为工程量清单中的各分部分项工程量并不十分准确，若设计深度不够则可能有较大的误差，而工程量的多少是选择施工方法、安排人力和机械、准备材料必须考虑的因素，自然也影响分项工程的单价，因此一定要对工程量进行复核。这里既然影响单价，则必然会影响总价。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]