[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139642":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139642,798,1,"单选题","根据《建设工程工程量清单计价规范》（CB50500-2013），施工企业综合单价的计算有以下工程，①确定组合定额子目并计算各子目工程量；②确定人、料、机单价；③测算人、料、机的数量；④计算清单项目的综合单价；⑤计算清单项目的管理费和利润；⑥计算清单项目的人、料、机总费用，正确的步骤是（）。（2016）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①-③-②-⑥-⑤-④",true,{"key":16,"text":17,"correct":18},"B","②-③-①-⑤-⑥-④",false,{"key":20,"text":21,"correct":18},"C","③-①-②-⑥-⑤-④",{"key":23,"text":24,"correct":18},"D","①-③-②-④-⑥-⑤","综合单价的计算可以概括为以下步骤: (1)确定组合定额子目 (2) 计算定额子目工程量 (3) 测算人、料、机消耗量 (4) 确定人、料、机单价 (5) 计算清单项目的人、料、机总费用 (6) 计算清单项目的管理费和利润 (7) 计算清单项目的综合单价 标题",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]