[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139635,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013）实行工程量清单计价的工程，应采用的合同类型是（）。 (2013)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总价合同",false,{"key":16,"text":17,"correct":18},"B","单价合同",true,{"key":20,"text":21,"correct":14},"C","固定总价合同",{"key":23,"text":24,"correct":14},"D","成本加酬金合同","实行工程量清单计价，应该采用单价合同。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]