[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139630":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139630,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013)，采用工程量清单招标的工程，投标人在投标报价时不得作为竞争性费用的是（ ). (2013)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程定位复测费",false,{"key":16,"text":17,"correct":18},"B","税金",true,{"key":20,"text":21,"correct":14},"C","冬雨季施工增加费",{"key":23,"text":24,"correct":14},"D","总承包服务费","安全文明施工费、税金和规费不得作为竞争性费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]