[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139625,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2008）。采用工程量清单招标的工程，投标人在投标报价时不得作为竞争性费用的是（） (2012)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","夜间施工费",false,{"key":16,"text":17,"correct":14},"B","施工排水降水费",{"key":19,"text":20,"correct":21},"C","安全文明施工费",true,{"key":23,"text":24,"correct":14},"D","二次搬运费","措施项目清单中的安全文明施工费应按照国家或省级、行业建设主管部门的规定计价，不得作为竞争性费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]