[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139615":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139615,798,1,"单选题","根据《建设工程工程量清单计价规范》GB50500-2013，投标人认为招标控制价编制不符合规范规定的，应在招标控制价公布后（ ）天内提交书面申请。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","10","本题考查的是投诉与处理。投标人经复核认为招标人公布的招标控制价未按照《建设工程工程量清单计价规范》GB50500-2013的规定进行编制的，应在招标控制价公布后5天内向招投标监督机构和工程造价管理机构投诉。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]