[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139614":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139614,798,2,"多选题","根据《建设工程工程量清单计价规范》，关于投标人其他项目费编制的说法，正确的有（）。2018真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","专业工程暂估价必须按照招标工程量清单中列出的金额填写",true,{"key":16,"text":17,"correct":18},"B","材料暂估价由投标人根据市场价格变动自主测算确定",false,{"key":20,"text":21,"correct":14},"C","暂列金额应按照招标工程量清单列出的金额填写，不得变动",{"key":23,"text":24,"correct":14},"D","计日工应按照招标工程量清单列出的项目和数量自主确定各项综合单价",{"key":26,"text":27,"correct":14},"E","总承包服务费应根据招标人要求提供的服务和现场管理需要自主确定","ACDE","本题考查的是投标报价的编制与审核。选项B，暂估价中的材料、工程设备必须按照暂估单价计入综合单价；专业工程暂估价必须按照招标工程量清单中列出的金额填写，不得随意修改。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]