[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139612,798,1,"单选题","根据《建设工程工程量清单计价规范》，某工程项目的钢筋由发包人在施工合同中约定与承包人一起招标采购，编制招标工程量清单时，招标人将HR335钢筋暂估价定为4200元\u002F吨，已知市场平均价格为3650元\u002F吨，若甲投标人自行采购，其采购单价低于市场平均价格，则甲投标人在投标报价时HR335钢筋应采用的单价是（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4200元\u002F吨",true,{"key":16,"text":17,"correct":18},"B","甲投标人自行采购价格",false,{"key":20,"text":21,"correct":18},"C","3650元\u002F吨",{"key":23,"text":24,"correct":18},"D","预计招标采购价格","本题考查的是投标价的编制与审核。发包人与承包人共同作为招标人对钢筋进行招标。其中HR335作为暂估价列入招标工程量清单。招标工程量清单中提供了暂估单价的材料、工程设备，按暂估的单价计入综合单价。所以招标人应根据招标工程量清单提供的暂估价金额填报综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]