[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139609,798,1,"单选题","招标方编制工程量清单时有以下工作:①确定项目编码:②研究招标文件，确定清单项目名称:③确定计量单位;④计算工程数量:⑤确定项目特征，正确的顺序是（）。2018真题",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①②③④⑤",false,{"key":16,"text":17,"correct":14},"B","①②⑤③④",{"key":19,"text":20,"correct":14},"C","②③⑤④①",{"key":22,"text":23,"correct":24},"D","②①⑤③④",true,"本题考查工程量清单计价的基本过程。工程量清单编制程序如图所示。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]