[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139607,798,1,"单选题","根据《建设工程工程量清单计价规范》GB50500-2013，投标人在确定分部分项工程的综合单价时，若出现某招标工程量清单项目特征描述与设计图纸不符，但均符合设计规范，应以（ ）为准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标工程量清单的项目特征描述",true,{"key":16,"text":17,"correct":18},"B","设计图纸及其说明",false,{"key":20,"text":21,"correct":18},"C","设计规范",{"key":23,"text":24,"correct":18},"D","实际施工的项目特征","本题考查的是投标报价的编制方法。在招投标过程中，若出现工程量清单特征描述与设计图纸不符，投标人应以招标工程量清单的项目特征描述为准，确定投标报价的综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]