[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139602,798,1,"单选题","（2020年真题）根据《建设工程量清单计价规范》，投标人可以根据需要自行增加列项的清单是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施项目清单",true,{"key":16,"text":17,"correct":18},"B","分部分项工程量清单",false,{"key":20,"text":21,"correct":18},"C","其他项目清单",{"key":23,"text":24,"correct":18},"D","规费、税金清单","P234-240 《建设工程工程量清单计价规范》GB-50500-2013规定：措施项目清单应根据拟建工程的实际情况列项。正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]