[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139600":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139600,798,2,"多选题","（2019年真题）根据《建设工程工程量清单计价规范》,投标人按照建设工程量清单填报投标价格时,必须与招标程量清单保持一致的有()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","项目编码",true,{"key":16,"text":17,"correct":14},"B","项目名称",{"key":19,"text":20,"correct":14},"C","计量单位",{"key":22,"text":23,"correct":14},"D","工程量",{"key":25,"text":26,"correct":27},"E","工程内容",false,"ABCD","P228-234 要求投标人必须按招标人提供的招标工程量清单填报投标价格，填写的项目编码、项目名称、项目特征、计量单位、工程量必须与招标工程量清单一致。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]