[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139598,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），不能列入其他项目清单的是（）。 （2016）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","专业工程暂估价",false,{"key":16,"text":17,"correct":14},"B","计日工",{"key":19,"text":20,"correct":14},"C","总承包服务费",{"key":22,"text":23,"correct":24},"D","总承包人自行分包管理费",true,"出现《建设工程工程量清单计价规范)) GB 50500-2013 未列的项目，可根据工程实 际情况补充。 1.暂列金额 2. 暂估价 3. 计日工 侧面理解，自行分包本就不合法，计价规范就更不会有这个项目存在了。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]