[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139596":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139596,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），下列费用可用暂列金额支付的是（）（2016）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主提出设计变更增加的费用",true,{"key":16,"text":17,"correct":18},"B","业主提供了暂估价的材料采购费用",false,{"key":20,"text":21,"correct":18},"C","因承包人原因导致隐蔽工程质量不合格的返工费用",{"key":23,"text":24,"correct":18},"D","固定总价合同中材料价格上涨费用","暂列金额是招标人暂定并包括在合同中的一笔款项。用于施工合同签订时尚未确定或者不可预见的所需材料、设备、服务的采购，施工中可能发生的工程变更、合同约定调整 因素出现时的工程价款调整以及发生的索赔、现场签证确认等的费用。 B中，业主提供了暂估价的材料采购费用，这部分作为材料费已含在综合单价中； C属于不能索赔的项目，施工单位自己承担。 D注意是总价合同，所以材料价格上涨费用施工单位自己承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]