[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139595":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139595,798,2,"多选题","根据《建筑工程量清单计价规范》(G B.50500-2013)，工程量清单计价计算公式正确的有( )。 (2014)",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","措施项目费=∑措施项目工程量×措施项目综合单价",false,{"key":16,"text":17,"correct":18},"B","分部分项工程费=∑分部分项工程量×分部分项工程综合单价",true,{"key":20,"text":21,"correct":18},"C","单项工程造价=∑单位工程造价",{"key":23,"text":24,"correct":14},"D","单位工程造价=∑分部分项工程费",{"key":26,"text":27,"correct":14},"E","建设项目总造价=∑单项工程造价+工程建设其他费用+建设期利息","BC","",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]