[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139591,798,1,"单选题","招标人编制工程量清单时，对各专业工程现行（计量规范）中未包括的项目应作补充，则关于该补充项目及其编码的说法，正确的是（ ）。 (2015)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该顶目编码应由对应《计量规范》的代码和三位阿拉伯数字组成",false,{"key":16,"text":17,"correct":18},"B","清单编制人应将补充项目报省级或行业工程造价管理机构备案",true,{"key":20,"text":21,"correct":14},"C","淸单编制人在最后一个清单项目后面自行补充该项目，不需编码",{"key":23,"text":24,"correct":14},"D","该项目按《计量规范》中相近的淸单项目编码","编制工程量淸单时如果出现《计量规范》附录中未包括的项目，编制人应做补充，并报省级或行业工程造价管理机构备案。补充项目的编码由对应计量规范的代码X(即01～09)与B和三位阿拉伯数字组成，并应从XB001起顺序编制。（比如：01 B001。）",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]