[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139586,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013)，招标工程量清单的准确性的完整性应由（）负责． (2013)",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投标人",false,{"key":16,"text":17,"correct":14},"B","招标人指定的招标代理机构",{"key":19,"text":20,"correct":14},"C","招标人的上级部门",{"key":22,"text":23,"correct":24},"D","招标人",true,"招标工程量清单必须作为招标文件的组成部分，由招标人提供，并对其准确性和完整性负责。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]