[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139583":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139583,798,2,"多选题","根据《建设工程工程量清单计价规范》GB50500-2013，下列清单项目中，应列入其他项目清单的有（ ）。2017真题",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","计日工",true,{"key":16,"text":17,"correct":14},"B","暂估价",{"key":19,"text":20,"correct":21},"C","材料二次搬运费",false,{"key":23,"text":24,"correct":21},"D","工程排污费",{"key":26,"text":27,"correct":14},"E","总承包服务费","ABE","本题考查的是其他项目清单的编制。其他项目清单应根据拟建工程的具体情况，参照《建设工程工程量清单计价规范》GB50500-2013提供的下列4项内容列项：（1）暂列金额；（2）暂估价：包括材料暂估单价、工程设备暂估价、专业工程暂估价；（3）计日工；（4）总承包服务费。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]