[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139579,798,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500-2013)，投标企业可以根据拟建工程的具体施工方案进行列项的清单是( )。 (2014)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",false,{"key":16,"text":17,"correct":18},"B","措施项目清单",true,{"key":20,"text":21,"correct":14},"C","其他项目清单",{"key":23,"text":24,"correct":14},"D","规费项目清单","本题考查的是投标报价审核方法。根据“计价规范”，分部分项工程量清单以及规费、税金，投标人必须执行招标工程量清单以及有关规定；其他项目清单中的暂估价、暂列金额，投标人必须执行。由于工程建设施工特点和承包人组织施工生产的施工装备水平、施工方案及其管理水平的差异，同一工程、不同承包人组织施工所采用的施工措施可能有所不同。因此，措施项目清单应根据拟建工程的实际情况列项。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]