[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139578,798,1,"单选题","根据《建设工程工程清单计价规范》，某工程项目设计文件中的部分工作内容不足以写进施工方案，但要通过一定的技术手段才能实现。2018真题此情况在编制工程量清单时，应列入（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程项目清单",false,{"key":16,"text":17,"correct":18},"B","措施项目清单",true,{"key":20,"text":21,"correct":14},"C","其他项目清单",{"key":23,"text":24,"correct":14},"D","规费项目清单","本题考查的是措施项目清单的编制。确定设计文件中不足以写进施工方案，但要通过一定的技术措施才能实现的内容应列入措施项目清单之中。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]