[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139575":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139575,798,1,"单选题","（2020年真题）关于采用定额单价法编制施工图预算时套用定额单价的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当分项工程的名称、规格、计量单位与定额单价中所列的内容完全一致时，可直接套用定额单价",false,{"key":16,"text":17,"correct":18},"B","当分项工程施工工艺条件与定额单价不一致而造成人工、机械的数量增减时，应调价不换量",true,{"key":20,"text":21,"correct":14},"C","当分项工程的主要材料品种与定额单价中规定材料不一致时,应按实际使用材料价格换算定额单价",{"key":23,"text":24,"correct":14},"D","当分项工程不能直接套用定额、不能换算和调整时，应编制补充定额单价","P226-231 分项工程施工工艺条件与定额单价不一致而造成人工、机械的数量增减时，一般调量不换价。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]