[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139574,798,1,"单选题","（2020年真题）某建设项目只有一个单项工程。关于该项目施工图预算编制要求的说法,正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应采用三级预算编制形式",false,{"key":16,"text":17,"correct":18},"B","应采用二级预算编制形式",true,{"key":20,"text":21,"correct":14},"C","不需编制施工图预算",{"key":23,"text":24,"correct":14},"D","编制建设项目总预算和单项工程综合预算","P225-226 当建设项目只有一个单项工程时，应采用二级预算编制形式，二级预算编制形式由建设项目总预算和单位工程预算组成。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]