[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139567":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139567,798,2,"多选题","施工图预算的编制依据有（）。 (2013)",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建设单位的资金到位情况",false,{"key":16,"text":17,"correct":14},"B","施工投标单位的资质等级",{"key":19,"text":20,"correct":21},"C","施工投标单位的施工组织设计",true,{"key":23,"text":24,"correct":21},"D","批准的设计概算",{"key":26,"text":27,"correct":21},"E","批准的施工图设计图纸","CDE","@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]