[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139561":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139561,798,1,"单选题","采用定额单价法编制施工的预算时，如果分项过程的某一种主要材料，单价中规定的材料品种不完全一致，该分项过程单价的确定方法是（） (2015)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按实际使用材料价格换算定额单价",true,{"key":16,"text":17,"correct":18},"B","直接套用同类材料的定额单价",false,{"key":20,"text":21,"correct":18},"C","调整工程量而不换算定额单价",{"key":23,"text":24,"correct":18},"D","编制补充定额单价","分项工程的主要材料品种与定额单价或单位估价表中规定材料不一致时，不可以直接套用定额单价；需要按实际使用材料价格换算定额单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]