[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139560":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139560,798,1,"单选题","采用定额单价法计算工程费用时，若分项工程施工工艺条件与定额单价不一致而造成人工、机械的数量增减时，对定额的处理方法一般是（ ). (2013)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制补充单价表",false,{"key":16,"text":17,"correct":14},"B","直接套用定额单价",{"key":19,"text":20,"correct":21},"C","调量不调价",true,{"key":23,"text":24,"correct":14},"D","按实际价格换算定额单价","分项工程施工工艺条件与定额单价或单位估价表不一致而造成人工、机械的数量增减时，一般调量不换价；",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]