[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139548":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139548,798,1,"单选题","拟建工程与在建工程预算采用同一施工图，但二者基础部分和现场施工条件不同，审查拟建工程施工图预算时，为提高效率，对其与在建工程相同部分宜采用的方法是（）。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","全面审查法",false,{"key":16,"text":17,"correct":14},"B","分组计算审查法",{"key":19,"text":20,"correct":21},"C","对比审查法",true,{"key":23,"text":24,"correct":14},"D","标准预算审查法","本题考查施工图预算审查的方法。拟建工程与已完或在建工程预算采用同一施工图，但基础部分和现场施工条件不同，则相同部分可采用对比审查法。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]