[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139546":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139546,798,1,"单选题","审查精度高、效果好，但工作量大，时间较长的施工图预算审查方法是（ ）。 (2012)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","逐项审查法",true,{"key":16,"text":17,"correct":18},"B","重点审查法",false,{"key":20,"text":21,"correct":18},"C","对比审查法",{"key":23,"text":24,"correct":18},"D","筛选审查法","逐项审查法 全面审查法又称逐项审査法，即按定额顺序或施工顺序，对各项工程细目逐项全面详细审查的一种方法。其优点是全面、细致，审查质量高、效果好。缺点是工作量大，时间较长。这种方法适合于一些工程量较小、工艺比较简单的工程。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]