[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139539,798,1,"单选题","某建设项目工程费用6800万元，其他费用1200万元，预备费500万元，建设期贷款利息370万元，铺底流动资金710万元。预计在建设中原房屋拆除变现收入100万元，试车收入大于支出金额150万元，则该项目总概算为（ ）万元。 (2015)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","9580",false,{"key":16,"text":17,"correct":18},"B","9330",true,{"key":20,"text":21,"correct":14},"C","9680",{"key":23,"text":24,"correct":14},"D","9430","总概算价值=工程费用+其他费用+预备费+建设期利息+铺底流动资金-回收金额； 回收金额是指在整个基本建设过程中所获得的各种收入。如原有房屋拆除所回收的材料和旧设备等的变现收入；试车收入大于支出部分的价值等。把数据带入可计算结果为B；",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]