[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139533,798,1,"单选题","当初步设计有详细设备清单时，编制设备及安装工程概算宜采用的编制方法是（ ). (2013)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","扩大单价法",false,{"key":16,"text":17,"correct":14},"B","概算指标法",{"key":19,"text":20,"correct":21},"C","预算单价法",true,{"key":23,"text":24,"correct":14},"D","类似工程预算法","预算单价法。当初步设计有详细设备清单时，可直接按预算单价（ 预算定额单价）编制设备安装工程概算。根据计算的设备安装工程量，乘以安装工程预算单价，经汇总求得。 用预算单价法编制概算，计算比较具伴，精确性较高。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]