[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139515":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139515,798,2,"多选题","（2020年真题）编制人工定额时，下列时间属于工人在工作班内必需消耗的时间有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","辅助工作时间",true,{"key":16,"text":17,"correct":14},"B","准备与结束工作时间",{"key":19,"text":20,"correct":21},"C","材料供应不及时引起的停工时间",false,{"key":23,"text":24,"correct":14},"D","工人在工作过程中恢复体力所必需的休息时间",{"key":26,"text":27,"correct":21},"E","施工组织不善造成的停工时间","ABD","P192-196",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]