[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139514,798,1,"单选题","（2020年真题）下列施工机械工作时间中，属于必需消耗的时间是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","低负荷下工作时间",false,{"key":16,"text":17,"correct":14},"B","多余工作和停工的时间",{"key":19,"text":20,"correct":21},"C","不可避免的无负荷工作时间",true,{"key":23,"text":24,"correct":14},"D","施工本身造成的停工时间","P198-200",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]