[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139512,798,1,"单选题","（2019年真题）按照单位工程量和劳动定额中的时间定额计算出的基本用工数量为15工日，超运距用工量为3工日，辅助用工为2工日，人工幅度差系数为10%，则人工幅度差用工数量为()工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1.5",false,{"key":16,"text":17,"correct":14},"B","1.7",{"key":19,"text":20,"correct":14},"C","1.8",{"key":22,"text":23,"correct":24},"D","2.0",true,"P197-200 人工幅度差用工数量=∑(基本用工+超运距用工+辅助用工)×人工幅度差系数=（15+3+2）×10%=2.0。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]