[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139510":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139510,798,2,"多选题","（2019年真题）下列机械工作时间中,属于机械工作必需消耗的时间有（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不可避免的无负荷工作时间",true,{"key":16,"text":17,"correct":18},"B","多余工作时间",false,{"key":20,"text":21,"correct":14},"C","有效工作时间",{"key":23,"text":24,"correct":18},"D","低负荷下工作时间",{"key":26,"text":27,"correct":18},"E","非施工本身造成的停工时间","AC","P192--194",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]