[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139505,798,1,"单选题","某施工企业编制砌砖墙人工定额，该企业有近5年同类工程的施工工时消耗资料，则制定人工定额适合选用的方法是（ ）。 (2015)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","技术测定法",false,{"key":16,"text":17,"correct":14},"B","比较类推法",{"key":19,"text":20,"correct":21},"C","统计分析法",true,{"key":23,"text":24,"correct":14},"D","经验估计法","制定人工定额 ，常用的方法有四种：技术测定法，统计分析法，比较类推法，经验估值法。 统计分析法是把过去施工生产中的同类工程或同类产品的工时消耗的统计资料，与当前生产技术和施工组织条件的变化因素结合起来，进行统计分析的方法。这种方法简单易行 ，适用于施工条件正常、产品稳定、工序重复量大和统计工作制度健全的施工过程。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]