[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139502,798,1,"单选题","完成某预算定额项目单位工程量的基本用工为2.8工日，辅助用工为0.7工日，超运距用工为0.9工日，人工幅度差系数为10%。该定额的人工工日消耗量为（ ）工日。 (2014)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4.84",true,{"key":16,"text":17,"correct":18},"B","4.75",false,{"key":20,"text":21,"correct":18},"C","4.56",{"key":23,"text":24,"correct":18},"D","4.68","人工幅度差用工数量=（基本用工+超运距用工+辅助用工）×（1+人工幅度差系数）=（2.8+1.7+0.9）×（1+10%）=4.84.",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]