[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139501":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139501,798,1,"单选题","某机械台班产量为4m3，与之配合的工人小组由5人组成，则单位产品的人工时间定额为（ ）工日。 (2013)",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0．50",false,{"key":16,"text":17,"correct":14},"B","0．80",{"key":19,"text":20,"correct":14},"C","120",{"key":22,"text":23,"correct":24},"D","1.25",true,"单位产品时间定额=小组成员工日数总和\u002F机械台班产量=5\u002F4=1．25。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]