[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139500":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139500,798,1,"单选题","编制预算定额人工消耗量时，人工幅度差是指人工定额中未包括的，而在一般正常施工情况下又不可避免的一些（）. (2013)",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","返工用工",false,{"key":16,"text":17,"correct":14},"B","低效率用工",{"key":19,"text":20,"correct":14},"C","用工浪费",{"key":22,"text":23,"correct":24},"D","零星用工",true,"人工幅度差用工。指人工定额中未包括的，而在一般正常施工情况下又不可避免的一些零星用工。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]