[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139498":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139498,798,2,"多选题","企业编制人工定额时要拟定施工作业的定额时间，应当包括在定额时间内的工人工作时间消耗有（ ） (2012)",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基本工作时间",true,{"key":16,"text":17,"correct":18},"B","施工组织不善造成的停工时间",false,{"key":20,"text":21,"correct":14},"C","辅助工作时间",{"key":23,"text":24,"correct":14},"D","不可避免的中断时间",{"key":26,"text":27,"correct":14},"E","准备与结束的工作时间","ACDE","施工作业的定额时间，是在拟定基本工作时间、辅助工作时间、准备与结束时间、不 可避免的中断时间以及休息时间的基础上编制的.",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]