[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139486":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139486,798,2,"多选题","编制过程周转性材料消耗定额时，影响周转材料消耗的因素主要有（ ）。2017真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","周转材料的制造工艺",false,{"key":16,"text":17,"correct":18},"B","周转使用次数",true,{"key":20,"text":21,"correct":18},"C","周转材料的最终回收及其回收折价",{"key":23,"text":24,"correct":14},"D","周转材料补损的难易程度",{"key":26,"text":27,"correct":18},"E","每周转使用一次材料的损耗","BCE","本题考查的是周转性材料消耗定额的编制。周转性材料消耗因素有：（1）第一次制造时的材料消耗（一次使用量）；（2）每周转使用一次材料的损耗（第二次使用时需要补充）；（3）周转使用次数；（4）周转材料的最终回收及其回收折价。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]