[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139482":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139482,798,1,"单选题","施工过程中对隐蔽工程质量检查验收影响工人操作的时间，属于预算定额人工消耗量指标组成中的（ ）。2017真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基本用工",false,{"key":16,"text":17,"correct":14},"B","辅助用工",{"key":19,"text":20,"correct":21},"C","人工幅度差用工",true,{"key":23,"text":24,"correct":14},"D","超运距用工","本题考查的是预算定额的编制。隐蔽工程验收等工程质量检查影响的操作时间属于人工幅度差用工。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]