[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139480":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139480,798,1,"单选题","编制人工定额时，工人定额工作时间中应予以合理考虑的情况是()。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由于水源或电源终端引起的停工时间",true,{"key":16,"text":17,"correct":18},"B","由于工程技术人员和工人差错引起的工时损失",false,{"key":20,"text":21,"correct":18},"C","由于劳动组织不合理导致工作中断所占用的时间",{"key":23,"text":24,"correct":18},"D","由于材料供应不及时引起的停工时间","本题考查的是人工定额的编制。施工本身造成的停工时间，是由于施工组织不善、材料供应不及时、工作面准备工作做得不好、工作地点组织不良等情况引起的停工时间。非施工本身造成的停工时间，是由于水源、电源中断引起的停工时间。前一种情况在拟定定额时不应该计算，后一种情况定额中则应给予合理的考虑。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]