[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139470,798,1,"单选题","（2020年真题）施工现场设立的安全警示标志，现场围挡等所需的费用属于（ ）费用",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施项目",true,{"key":16,"text":17,"correct":18},"B","分部分项工程",false,{"key":20,"text":21,"correct":18},"C","零星项目",{"key":23,"text":24,"correct":18},"D","其他项目","P167-172 措施项目费是指为完成建设工程施工，发生于该工程施工前和施工过程中的技术、生活、安全、环境保护等方面的费用。 临时设施费:是指施工企业为进行建设工程施工所必须搭设的生活和生产用的临时建筑物、构筑物和其他临时设施费用。包括临时设施的搭设、维修、拆除、清理费或摊销费等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]