[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139455":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139455,798,1,"单选题","编制建设项目投资估算时，考虑项目在实施中可能会发生涉及变更增加工程量，投资计划中需要事先预留的费用是（ ） (2012)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","涨价预备费",false,{"key":16,"text":17,"correct":14},"B","铺底流动资金",{"key":19,"text":20,"correct":21},"C","基本预备费",true,{"key":23,"text":24,"correct":14},"D","工程建设其他费用","基本预备费 基本预备费是指在项目实施中可能发生难以预料的支出，需要预先预留的费用，又称不可预见费。主要指设计变更及施工过程中可能增加工程量的费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]