[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139452":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139452,798,1,"单选题","某建设工程项目建筑安装工程费为2000万元，设备及工器具购置费为800万元，工程建设其他费用为300万元，基本预备费率为8%，该项目的基本预备费为（）万元。（2016）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","160",false,{"key":16,"text":17,"correct":14},"B","184",{"key":19,"text":20,"correct":21},"C","248",true,{"key":23,"text":24,"correct":14},"D","224","基本预备费=（工程费（建筑安装工程费、工器具购置费）+其他费）*基本费费率",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]